• Client :Montréal Olympic Park
  • Architecture :Lemay + ACDF architecture
  • Entrepreneur :Canam / Pomerleau
  • Budget :$870 M
  • Photos Credits :SNAPePHOTO

A major, historic project involving the complete renewal of the Olympic Stadium’s existing tensioned fabric roof, and the replacement of the existing precast/prestressed concrete technical ring with a fixed structural steel roof that includes a glazed halo.

ELEMA’s engineering services are provided as part of the design-build team led by the Groupe Canam-Pomerleau consortium (GCPC), working notably with Walter P Moore (WPM), a U.S. firm specializing in stadium structures. Our key role as structural engineers on this iconic project has deepened our understanding of many aspects of the stadium: its history, the ideas behind its architectural genesis, its structural design (including the interaction between the stadium structure and the tower), and the Olympic Park project team.

Our mandate on this complex project covers the analysis, design, modelling, coordination, and preparation of drawings and specifications for the new technical ring, the perimeter structural interface between the new roof and the existing stadium structure. ELEMA was responsible for engineering the new steel technical ring – which is much lighter than the original concrete ring – and designed it to redistribute roof loads to the 38 existing consoles. Working closely with Walter P Moore, ELEMA ensured structural compatibility between the ring and the roof within a unique inclined ovoid geometry, under northern climate conditions.

Panoramic glass railing of the Montréal Tower

Alongside the new roof project, major redevelopment work is under way in the Montréal Tower (the Olympic Stadium’s mast) which includes the ground-floor reception area, the replacement of the funicular, and the revamped observatory at the top. Our firm is involved in creating a new observation space on the roof of the mast, specifically a new cantilevered panoramic structural glass railing that promises quite a thrill.

For more information…


Technical challenges :

  • Accelerated design-build schedule: A comprehensive preliminary phase defined the project’s critical parameters and cost. Sequencing the work (preliminary works, deconstruction, tower niche, ring fabrication and installation, buttresses, inner and perimeter roofs) helped keep the pace.
  • Complex interdisciplinary coordination: North American and European teams, plus integration of the Olympic Park’s electromechanical and scenographic systems. The ring segments were fully prefabricated (structure, integrated AV and HVAC systems, cladding). Clash detection in Navisworks, with progressively tighter tolerances, eliminated all conflicts before fabrication.

Notable solutions and innovations :

  • Integrating the new technical ring with the existing consoles: The 38 concrete consoles showed variations in position caused by original construction inaccuracies, thermal effects, creep and relaxation. The solution was a bolted interface with slotted holes and adjustment shims, allowing adjustment along all three axes. It was supplemented by a monitoring and prediction model fed by periodic surveys.
  • Complex technical ring geometry: The geometry required advanced BIM modelling and parametric programming. Full-scale mock-ups of the main components were built to validate the solutions before implementation.