The construction site for the excavation of the STM’s Bellechasse Transport Center is advancing at a high speed! 

After the demolition of the existing building, the installation of the temporary retaining walls and the excavation of the existing soils, all is ready for blasting! Rock excavation work is expected to reach a depth of nearly 20 m (65 ft) for a volume of nearly 300,000 m3 (10,594,400 ft3).