• Date : January 21, 2021
  • Share :

Following a site visit this morning to the MAA project, we present you photos showing the complete stripping of the foundations under the existing facades, supported by the system we’ve designed. This accomplishment is carried out by the Vespo/Ramsol team.

This major intervention is required in order to allow the excavation of three new floors of underground parking. To get an idea of ​​the scale of the mandate, observe the worker to the right of the photo!

Clients : Devimco / Edyfic
Architect : LEMAYMICHAUD

[-] For more construction site photos…


[-] For more information about the structural challenges of the temporary support structure and the new 35-storey tower…