• Date : June 25, 2019
  • Share :

The multiple structural interventions on this existing building (including the complex temporary support of the columns in the basement and the assembly of the three new steel floors on the roof) are being completed!

The attached image shows the progress of the new northeast corner of the project where 13 new concrete floors with an individual surface area of ​​475 m² (5,100 ft²) have been added.

For more information about the project…